Tampomas Geothermal Power Plant Development Plan

EXPLORATION

EXPLOITATION

2009-2012

2013-2014

2015

2016

2017

SURVEY

DRILING

FINISH

IN PROGRESS

  • Mining Area & Mining Licence

  • Organizing the Projection

  • Standard Operating Procedures

  • GNG Implementation

  • Environmental Management Effort - Environmental Monitoring Effort

  • Land Acquisition

  • Infrastructure Plan

  • Exploration Drilling

  • Report & Evaluation

  • Pre Feasibility Study

  • Preparation of EIA

  • Geothermal Power Plan Design

  • Exploration Drilling

  • NOID

  • The Geothermal Power Plan FEED

  • EPC Tender

  • Exploitation Drilling

  • Built the Power Plant Construction

  • Built the Geothermal Power Plant Construction

  • Commissioning

  • COD (Commercial Operation Date)



long term plan

According to our vision to be a geothermal company which has 500 MW capacity in 2022, Sari Prima Energi will continuously make a progress to be the leading company by acquiring share of exploration stage company or participating in the tender for new work areas. By the end 2013, Sari Prima Energi is expected to have majority stocks in three working areas.